ACE ridwithus podcast
05:20 - Boardwalk project scope has expanded, which is part of why the coaster hasn't been announced yet. Ryan notes that this teasing-style approach is unconventional for legacy CF. Since the scope has expanded, there is/was additional creative work required (logos/backstories/concepts/names/etc), which has led to delays in some items that were set aside to work on others. Since the boardwalk improvements will be realized first, they wanted to have those announcements/theming/etc ready.
09:25 - Rides (and the '27 coaster) will likely start construction between March/April with progress by Memorial Day weekend.
21:10 - New coaster to be announced in the next two to three months, and should be able to give Ka a subtle nod at that point.
29:55 - Ride would've been announced in August on a normal rollout timeline.