Given that Cedar Fair has a habit of setting attraction anouncement dates based on what is usually the major capital expenditures for the following year, I am not sure that a major coaster is in the works for KD in 2024.
I am not saying that we are getting nothing for 2024, just no major coaster next year. Plus, we are way past the construction timeline for a major coaster. If one was going in the mountain spot, KD would have needed to clear out the land in the spring and start grading the land. June would have seen the start of pouring concrete footers. By mid-late July, coaster supports/track would start arriving. Erecting the supports/track would start in August, etc. Right now, we have a location that some folks have reported utility markings and some bit of barrier construction on site.That is the extent of any site changes at this point.
If KD were to get a flat ride package in 2024, I could see an announcement in mid to late August.