RE: Mäch Tower

Where the two fences meet right before the bridge. Put your head through it and then look to your left. You get a great view of what's going on.
 
RE: Mäch Tower

This is pretty much it:

 

Attachments

  • DSC_0062.JPG
    DSC_0062.JPG
    304.9 KB · Views: 94
RE: Mäch Tower

Sooooo has anybody heard a opening date for this?
Do you think it will be open for pass member day ?
 
RE: Mäch Tower

I doubt it whenever they open a attraction it usally opens on memorial day.
 
RE: Mäch Tower

I imagine Memorial day weekend (give or take a few weeks) would be the opening date, but they could have a soft opening a few weeks prior.
 
RE: Mäch Tower

jan, feb, march. I hope I can go around Memorial Day... If and only if the whole attendance swarms mach tower that opening week, then that means less of a wait for the other coasters!
 
RE: Mäch Tower

Take in account the time to pour and accurately set the foundation, lay base mounts and pour over those, dry time, then electrical and pneumatics, base, and upward. I think Mid-End February we should start seeing it in the skyline. My timeline is based upon the reviewals of other DT constructions.
 
RE: Mäch Tower

^Good news with that timeline is most of the rebar was in place for the foundation at the end of Christmas Town
 
RE: Mäch Tower

From what I could see when I went was they had a lot for rebar to lay. Think of how sturdy that foundation is going to have to be in order to accommodate such an immense single tower. The foundation requires to be different than that of a tall coaster hill since coasters feed off the adjacent supports and are not of a freestanding nature.
 
RE: Mäch Tower

Well we also don't know how deep that hole is. Depending on the depth of that hole most of the foundation could have already been laid but out of the sight of many of us walking around the park.
 
RE: Mäch Tower

The basic schedule that I saw was:

Phase 1:
November 1, 2010 - Jan 1, 2011
Ride foundations and utilities
Building foundations and utilities

Phase 2:
Jan 1, 2011 - March 2011
Entire site inclusive of any accepted alternates

Phase 3:
March 2011 - April 2011
Final ride erection
Building open to guests.

So by this the foundations should be done. They only have one to two months slotted for the actual ride construction. One of the alternates was putting the scrambler in New France. I don't know which alternates were accepted but I would have to think this is one of them.
 
RE: Mäch Tower

Just saying that concrete takes 28 days to fully cure, so it might take a month just for the concrete to be fully done.
 