I mean kinda, I don’t know the exact weight of a track segment but it most likely will require a lull or a wheel loader, and that’s not something I would imagine the park has, then you have the argument of who should unload vs who will unload, the steel erectors should be the ones handling it, do they want to stage a crew on site to just unload steel? I can go on and on. My take on it is if I was project managing this, I would most likely tell them to store everything I could at the fabricators as long as they would let me until they forced me to take it and that way I could have the crew in charge of unloading and staging on site for the shortest time possible while getting the most amount of possible work done. At the end of the day to them it’s not a rollercoast it’s another project and they have to save every dollar.