RE: Project Madrid: New Hamlet? Giga Coaster? 315' Tower?
Aren't EIS's done only for publicly owned projects (i.e. roadway projects)? From what I have seen in the past with Busch projects and other private land development projects are height waivers, site plans, and special use permits (if the land use doesn't match the zoning). After doing some digging a while ago, I found the submittal dates for past major projects at Busch:
With all of that being said, I believe that the site plan will be the biggest indicator as to when we will expect to see an opening. From all of the past projects, opening dates were roughly one year after the site plan was submitted to the county (with the exception of Verbolten, which was a year and three months). Also, site plans were submitted anywhere from 2 days to five months after height waiver approvals, thus if history is any indication, we should see a site plan submitted to the county by the beginning of 2018. With the past timelines, this should put the opening of the attraction in 2019. Also, so far the longest time between height waiver submission and opening of the attractions has been a year and a half - also pointing towards a 2019 opening, unless this is an attraction with much larger scale than previous ones.
Side note: I couldn't find much information about when submissions/approvals occurred for InvadR. I also don't think there was a height waiver submitted for the project.
warfelg said:If I had to put forth my best guess for the timeline from here (this is what I did before leaving planning department in local government)
~11/2017 the Notice of Intent for an EIS (Environmental Impact Statement) is filed, this is where the public can become involved, learn about the scope of the work, and alternatives that would be less impactful the work is.
~4/2018 Notice of Intent wraps up and a draft of the EIS is published for public review, has to stay up for 45 days.
~6/2018 Final EIS is published, where again it has to wait at least 30 days before it can become finalized.
~7/2018 Any field pens that need to be moved are moved, clean up of ground level growth
~8/2018 Utilities marked/Trees for removal marked
~10/2018 Trees start coming down, open field foundations start being dug.
~11/2018 Foundations start to get poured
All of 2019 construction happens
Aren't EIS's done only for publicly owned projects (i.e. roadway projects)? From what I have seen in the past with Busch projects and other private land development projects are height waivers, site plans, and special use permits (if the land use doesn't match the zoning). After doing some digging a while ago, I found the submittal dates for past major projects at Busch:
- Apollo's Chariot - Height Waiver submitted 10/7/1997, Height Waiver approved 12/9/1997, Site Plan submitted 3/20/1998, Opened 3/30/1999. Height Waiver Approval (pg. 5)
- Griffon - Height Waiver submitted 1/23/2006, Height Waiver approved 4/11/2006, Site Plan submitted 4/19/2006, Opened 5/18/2007. Special Use Permit for Expansion Approval (pg. 127)
- Mach Tower - Height Waiver submitted ??/??/2010, Height Waiver approved 6/8/2010, Site Plan submitted 7/20/2010, Opened 8/18/2011. Height Waiver Approval (pg. 55)
- Verbolten - Height Waiver submitted 11/24/2010, Height Waiver approved 2/8/2011, Site Plan submitted 2/10/2011, Chesapeake Bay Board meeting 3/9/11 (for RPA buffer impacts), Opened 5/18/2012. Height Waiver/Special Use Permit Approval (pg. 43)
- Tempesto - Height Waiver submitted 10/7/2013, Height Waiver Approved 11/12/2013, Initial utility markings requested 2/20/2014, Site Plan submitted 4/21/2014, Opened 4/25/2015. Height Waiver Approval (pg. 73)
- Project Madrid - Height Waiver submitted 6/29/2017, FAA submittal 7/5/2017, Initial utility markings requested (assumed to be for this project) 7/19/2017, Height Waiver approved 8/8/2017, FAA approval 9/18/2017. Height Waiver Approval (pg. 67)
With all of that being said, I believe that the site plan will be the biggest indicator as to when we will expect to see an opening. From all of the past projects, opening dates were roughly one year after the site plan was submitted to the county (with the exception of Verbolten, which was a year and three months). Also, site plans were submitted anywhere from 2 days to five months after height waiver approvals, thus if history is any indication, we should see a site plan submitted to the county by the beginning of 2018. With the past timelines, this should put the opening of the attraction in 2019. Also, so far the longest time between height waiver submission and opening of the attractions has been a year and a half - also pointing towards a 2019 opening, unless this is an attraction with much larger scale than previous ones.
Side note: I couldn't find much information about when submissions/approvals occurred for InvadR. I also don't think there was a height waiver submitted for the project.